December 7, 2015; The Painting project wraps up with the final spots at the peak painted using a 40' lift. ... [Continue Reading]
SCC Progress: Water remediation work begins
Nov 18, 2015 Work begins on remediation of future water infiltration effecting our repairs and painting of the ... [Continue Reading]
SCC Progress: Demo begins in classrooms
Feb 28, 2017 "How does our rector bless the SCC building project?" by making it holy... Cat takes the first ... [Continue Reading]
SCC Progress: New stove for the kitchen
Jul 27, 2016 As part of the SCC's kitchen plans and by the blessing of Penny Johnson writing a grant request our Diocese ... [Continue Reading]
SCC Progress: Drilling the ground water monitoring well
SCC: Progress Recovering Insulation
Apr 8, 2017 The work to remove the ceiling in the center two classrooms started with the removal and recovery of the ... [Continue Reading]
SCC Progress: Back entrance grading begins, Welcome Smith Students
SCC Progress: Classroom’s original ceiling exposed
April 15, 2017: Ivy, Greg, Lee, Judson, helped Shawn Allen remove the last layer of drywall to expose the original chapel ... [Continue Reading]
SCC Progress: Insulation donated to family in Irving
April 13, 2017: Ben posted our 85 bags of cellulose insulation removed from the class room's ceiling on Freecycle and it ... [Continue Reading]
SCC Progress: Prep for Easter Too
April 21, 2017 rain stayed away for the unloading of our lumber, all smile. The wall panels take shape ... [Continue Reading]